Warehousing and storage across India · 77+ Warehouses · 1M+ Sq. Ft. Live Space

Heavy equipment & project cargo warehousing

Oversize, under cover. Every position agreed first.

Fabricated frames, skids and crated machinery wait here out of the weather while sites catch up — each unit measured in, positioned once, released as the build schedule allows.

Find Warehouse
Warehouses
34
Locations live
25
Collection centres
74
States & UTs
19
ENGG

01 · One unit, one line

Measured before
it ever arrives.

Arrival day runs to a plan, not an improvisation: dimensions, weight and crating checked against the papers, the unit tied to its project reference, spares labelled to the same line.

Pick face, level two · sample slot

What the register holds on one machine

Item ref
EQ-2410-058
Position
FLOOR-D04
Units
1 machine, 2 skids
Status
Held for site

Sample record, shown to illustrate how a project unit is logged — not a live Lozy figure.

Site programmes slip and foundations wait, so a machine may sit for months. A register tying each unit, its control panels, crates and manuals to a single release plan keeps dispatch matching the site as dates move.

02 · Fab shop to site

Off the low-loader,
into the build order.

01 / 08

One crated machine, waiting out the site's delay — a sample drawing.

  1. 01

    Inbound

    Every arrival follows a plan made before the item leaves the fabricator — route, access and standing area settled.

  2. 02

    Receive

    Measurements and weights checked against the drawings, crating examined, and one register line opened for the unit.

  3. 03

    Store

    Settled onto its planned floor position, under cover, skids kept square so nothing leans across a long wait.

  4. 04

    Pick

    The site's release plan decides what moves next; the unit is checked with its spares and manuals alongside.

  5. 05

    Pack

    Protective covering refitted, every brace re-secured, and the crate's fastenings confirmed before the trailer door closes.

  6. 06

    Label

    Project reference stencilled on every crate, so a load cannot land at the wrong stage of the build.

  7. 07

    Dispatch

    Moves out in the agreed sequence, papers cross-checked against the register on the way out.

  8. 08

    Delivery

    Handed over at the site gate only once the build is ready for it.

03 · Sites and depots

Staged together,
released by build order.

Foundations, structure and fit-out for several sites wait in one building, each release sequenced to that site's own order — so nothing lands early.

  • EPC contractors
  • Project sites
  • Fabrication shops
  • OEM plant teams
  • Service depots
03 · The warehouse LOZY WAREHOUSE
  1. 01 Staged release
  2. 02 Lozy warehouse
  3. 03 Pick
  4. 04 Pack
  5. 05 Ship

04 · Space for oversize

What stands
under a Lozy roof.

A heavy equipment warehouse holds finished machines, structures and the parts that travel with them. A typical storage plan covers deliverable items, project spares and the crates and frames that protect everything in transit between factory and site, or depot:

Inside a Lozy warehouse — Engineering & Heavy Equipment storage
Inside a Lozy facility
  • 01Machines and production equipment
  • 02Fabricated steel structures
  • 03Skids, base frames and mounts
  • 04Control panels and drive units
  • 05Pipes, beams and long sections
  • 06Crated assemblies and sub-assemblies
  • 07Site fixtures and fit-out material
  • 08Project spares and service kits
  • 09Tools and site consumables
  • 10Transport crates and support frames
  • 11Operation manuals and drawings

Oversized, unusually shaped or heavy items are reviewed before booking so the storage position and access can be planned. Share dimensions, weights and site dates when you enquire.

Need space for Engineering & Heavy Equipment stock?

Tell us what you store and where it needs to reach — the team confirms availability, the plan and the rates in writing.

WhatsApp Us Call Now

05 · When site dates slip

Every industry carries its own pressure — these are the ones the space, the handling and the paperwork are planned around.

  • 01

    Ordinary godowns cannot cope

    Machinery and fabricated structures do not fit standard shelf racks or stack neatly. An ordinary godown forces them into corners, where they block access, gather dust and become far harder to inspect or retrieve later.

  • 02

    Long lead times tie up space

    Equipment ordered for a project can sit for months before the site is ready. Without a plan that treats it as long-term storage, items get shuffled between places and paperwork goes missing along the way.

  • 03

    Movement needs planning

    Oversized items cannot be shifted on a whim. Access routes, clearances and the final position need thought before the trailer arrives, or the item ends up parked wherever it happens to land.

  • 04

    Dust and weather damage

    Monsoon rain, dust and standing moisture are hard on machinery surfaces, electricals and crated assemblies. Uncovered yards and leaking sheds turn working equipment into a refurbishment project before it reaches site.

  • 05

    Site dates keep shifting

    Civil work runs late, foundations wait on approvals and dispatch plans change weekly. Storage that cannot hold material longer, then release it in a new sequence, pushes the problem straight back to the project team.

  • 06

    Small parts get separated

    Control panels, fasteners, mounts and manuals often arrive with the main machine but are easier to misplace. Once separated, reconnecting the right parts to the right equipment becomes a project in itself.

06 · Room for the wait

Plan first,
protected throughout.

5 operations, one contract. Pick one to see what it covers.

07 · Getting started

From enquiry
to moving in.

Heavy equipment enquiries start with dimensions, weights and site dates. The team reviews the access route and agrees a handling plan before the first item arrives, so its storage position is settled while the trailer is still being loaded.

  1. 01 Enquire

    Share your product type, volumes and the city you need. The team confirms availability and shares rates in writing.

  2. 02 Site visit and requirement planning

    Visit the shortlisted facility or plan remotely — space, access and handling are matched to your operation.

  3. 03 Onboarding

    Documentation, check-in records and access setup are completed before your stock arrives, so day one runs clean.

  4. 04 Storage, fulfilment and dispatch

    Stock is stored, managed and dispatched per your instructions, with monthly GST-invoiced billing.

08 · Why firms come back

  • 01

    1M+ Sq. Ft. Live Space across our network gives project consignments room to be stored, staged and released properly.

  • 02

    Handling and placement planned around each item's dimensions, weight and dispatch sequence, so arrival day is a settled operation.

  • 03

    Staged dispatch aligned to site readiness, with release lists agreed and sequenced to match the project's actual build order.

  • 04

    Billing stays predictable with monthly billing, GST invoice, no lock-in, so a project that runs long does not force a fresh negotiation.

09 · Coverage

Store here.
Deliver everywhere.

Warehousing sits where the orders are. Lozy runs 74 collection centres across 19 states and union territories — store in the right city and the last mile gets shorter.

Lozy network · 74 centres, 47 cities
Boundary as India officially depicts it
  1. 01 Warehouse
  2. 02 Fulfilment
  3. 03 Distribution
  4. 04 Customer

Every lane on the map is a real movement: stock received at a Lozy warehouse or collection centre, picked and packed there, then distributed to the customer — or moved between sites to be closer to demand.

Guwahati · Jorhat · Bengaluru · Patna · Coimbatore · Madurai · Puzhal & Ambattur · Red Hills (Chennai) · Sholavaram · Ahmedabad · Ankleshwar · Vapi · Ambala · Dharuhera · Faridabad · Garhi Harsaru · Jamalpur · Sonipat · Hyderabad · Jammu · Srinagar · Ranchi · Cochin · Indore · Aurangabad · Bhiwandi · Nagpur · Nashik · Pune · Alipur · Bamnoli · Dhulsiras · Bhubaneswar · Cuttack · Chandigarh · Ludhiana · Zirakpur · Jaipur · Ballia · Ghaziabad · Lucknow · Noida · Haridwar · Roorkee · Rudrapur · Kolkata · Siliguri

10 · Before the trailer

Before you
start storing.

The questions Engineering & Heavy Equipment teams ask before taking warehouse space — answered in plain words.

What does heavy equipment warehousing with Lozy involve?

Lozy stores machinery, fabricated structures and oversized project items in covered facilities, with handling and placement planned around each item's dimensions and weight. Consignments are protected from dust and weather and released in phases against project site schedules, billed monthly across Delhi NCR and our India network.

What is heavy equipment warehousing?

Heavy equipment warehousing is the storage of machinery, fabricated structures and other oversized project items in a managed facility. Because these items are difficult to move and costly to damage, handling plans and storage positions are agreed before arrival, and dispatch follows the project's site schedule.

Key points

  • Covered storage areas sized for machinery, fabricated structures and crated assemblies
  • Handling and placement plans agreed before each item arrives at the facility
  • Long-lead project storage with phased dispatch in line with site readiness
  • Equipment kept off damp floors and covered against dust and monsoon weather
  • Monthly billing that suits project timelines, with GST invoices issued

How handling plans work in heavy equipment warehousing

Every oversized item comes with three questions: how does it get in, where does it sit, and how does it come out. The process works when those answers are agreed before the trailer is loaded. Dimensions, weight distribution, access needs and the dispatch sequence are reviewed together, and the storage position is chosen so the item can be retrieved later without disturbing its neighbours. That planning is what keeps a machinery consignment from becoming an obstacle course in a shared warehouse.

Staging long-lead equipment before a project starts

On long projects, equipment is often ready well before the site is. Storing it well means treating the warehouse as a staging area: items checked in against the project register, kept under cover, and released in the order the site can actually receive them. Foundations, structure and fit-out follow each other in a sequence, and a dispatch plan that matches construction reality saves rehandling and stops expensive items sitting exposed on site for months.

What drives the cost of heavy equipment storage

Billing is monthly, based on the floor space your items occupy and the handling they need, with GST invoices for registered businesses. Rates depend on location, the term, access requirements and how densely items can be stored, and the team quotes in writing after a requirement check or a site walk-through. The comparison worth making is not rate alone: equipment stored without cover or planning costs far more in refurbishment than a slightly higher rate on the right space.

How to choose a warehouse for Engineering & Heavy Equipment

Choosing storage for machinery is mostly about the day the item arrives and the day it leaves. These checks help project and plant teams avoid the common mistakes in between.

Route and access reviewed first

Ask how the path from gate to storage position is planned: turning space, door widths, floor route and final placement. If access is treated as an afterthought, the item is parked wherever it happens to fit.

A handling plan before arrival

The right time to plan movement is before dispatch, when the item can still be packed and braced for storage. Confirm exactly what information the facility needs from your project team.

Floor space for irregular shapes

Machinery and fabricated frames rarely stack. Look for clear floor areas that suit their footprints and heights, with walkways kept open so stored items can still be inspected and counted.

Protection from dust and weather

Covered storage, items raised off damp floors and adequate wrapping slow the wear that turns functional equipment into a refurbishment task before it ever reaches the site. Ask what covering is included.

Long-lead storage terms

Projects slip, so confirm how extended storage is billed, how often the arrangement is reviewed, and what notice is needed before a partial release or the final dispatch to site.

Staged dispatch readiness

Ask how release lists are sequenced and how quickly an item can be readied for transport once the site gives clearance, especially when several items leave in one dispatch slot.

Records that outlast the project

Check-in notes, condition observations and an inventory list at the facility should match your own project register, so final reconciliation takes an afternoon rather than a month of emails at close.

Frequently asked questions

What kinds of equipment can be stored with Lozy?
Typical items include production machines, fabricated structures, control panels, skids, base frames, crated assemblies and project spares. Share dimensions, weights and photos when you enquire and the team will confirm what suits the available space.
How is oversized equipment moved into and around storage?
Movement is planned item by item in advance: the access route, clearances and final storage position are agreed, and that plan is followed on arrival. Requirements are reviewed before storage is confirmed, so there are no surprises on the day.
Can equipment be stored for many months before dispatch?
Yes. Long-lead project storage is common: items stay under cover, are reviewed at agreed intervals and are released when the site is ready, billed monthly so the arrangement moves with the project timeline.
How much does heavy equipment storage cost with Lozy?
Plans start at ₹12 per sq ft per month, and the final rate depends on the space your items occupy, the location, the term and the handling they need. The team confirms a written quote after reviewing the requirement.
How is equipment protected from dust and weather?
Items are kept under cover and off damp floors, with wrapping and covering retained or refreshed where needed. Storage positions avoid leak paths and busy movement routes, so machinery surfaces and electricals stay in working condition.
Can dispatches be staged to match project site progress?
Yes. Provide a release list and the team readies each item in the agreed sequence, so foundations, structures and fit-out equipment arrive when the site can receive, store and install them.
Do you store smaller components along with the machinery?
Yes. Control panels, spares, fasteners and manuals can be stored in the same consignment and labelled against the parent equipment, so nothing gets separated or difficult to match at the dispatch stage.
What information do you need before accepting an oversized item?
Dimensions, approximate weight, access requirements and the intended dispatch sequence help the team plan placement properly. Photos and drawings also help, so share whatever is available at the enquiry stage.
Is interim storage available between factory and site?
Yes. Equipment can wait safely between production and installation, whether that gap is weeks or months. Monthly billing makes interim storage practical instead of forcing an early delivery the site cannot receive.
Can imported machinery be stored after clearing?
Imported project cargo can move from clearance into storage with customs and import-export support through Lozy's customs desk, so equipment is received, checked in and held until the site is ready for it.

11 · Dimensions first

Foundations run late.
Covered storage, staged release.

Send the item list, weights and release dates.

Speak to a human · +91 9354712345

12 · Enquiry

Tell us what
you need to store.

Availability, plan and rates — one short form, a written reply.

  • Tell us the industry, product and city — one short form or call.
  • Get availability and rates in writing, itemised.
  • Move in with documentation, access and records done before stock arrives.
Or call +91 9354712345 · WhatsApp us any working day.

Contact our experts

One form, one reply — Engineering & Heavy Equipment availability and rates.